Sydenham Road skyline, April 2010

Latest updates
When will the next bus arrive? PDF Print E-mail
Tuesday, 09 February 2010 10:35

Good news for local bus passengers. Transport for London (TfL) has announced that two pairs of bus stops in central Sydenham will be fitted with dot matrix countdown indicators – visual displays which show how long it is before the next bus arrives. In 2011, the stops outside Boots and outside LA Fitness (plus the bus stops on the other side of the road) will be fitted with the new indicators.

Last Updated on Saturday, 06 March 2010 18:52
 
EMPTY SHOPS ON SYDENHAM ROAD SURVEY PDF Print E-mail
Sunday, 07 February 2010 16:26

We all look on with dismay every time an empty shop appears on the high street. But just how many empty shops are there? And should we be concerned?

Last Updated on Saturday, 06 March 2010 18:52
Read more...
 
SYDENHAM ROAD IMPROVEMENT SCHEME PDF Print E-mail
Friday, 29 January 2010 14:52

A £4.7m scheme to improve Sydenham Road will be underway by August. Lewisham’s Mayor and Cabinet committee gave the go-ahead to the scheme on Wednesday evening (20 January), so now it’s down to the tendering and construction phases, starting with improvements to Station Approach.  And the good news is that the eastern end of the high street – from Mayow Road to Kent House Road - is also included in the revamp. The scheme will work as follows:

Cobb’s Corner to Mayow Road

  • £3.6m scheme to improve the core section of the high street.
  • This includes £310,000 to improve Sydenham Station Approach.
  • At the recent public exhibition 957 people completed comment cards. In response to the question – Do you support the proposals overall? – 89% answered yes; 6% No; 5% don’t know and 1% gave no answer.

Mayow Road to Kent House Road

  • A £1.1m scheme to improve the “lower” section of the high street.

Timetable

  • 20 January 2010
Both schemes approved by Mayor and Cabinet
  • March 2010
List of tenderers agreed
  • May 2010
Tenders issued
  • July 2010
Tender evaluation results reported to Mayor and Cabinet
  • August
Work commences
  • November  2010 to Mid January 2011
Minimal disruption works - side streets, Station Approach etc.
  • August 2011
Works completed Cobb’s Corner to Mayow Road
  • August 2011 to August 2012
Works completed Mayow Road to Kent House Road

Barry Milton

Roads & Transport Committee

Last Updated on Friday, 29 January 2010 21:56
 
PDF Print E-mail
Monday, 01 February 2010 14:48

Got an Old Mattress? Recycle, don't dump it!

 
 
 
 
6,710 old mattresses were dumped on the streets of the borough in the last five months of 2009. Now, in an effort to combat this anti-social behaviour, Lewisham Council are pioneering a new scheme  - the first of its kind in the UK - to collect old mattresses and recyle them responsibly and at no extra cost to residents. To use the free mattress recycling service:
 
  • collect a sticker from Lewisham Council's Access Point or at a local library 

  • place the sticker on the mattress 

  • put your old mattress by your bin, the night before your refuse collection day
 
 
 
For further information:
 
020 8314 7171
 
 
Last Updated on Monday, 01 February 2010 15:23
 
ELL to open 23rd May / Other Rail Updates! PDF Print E-mail
Wednesday, 20 January 2010 13:16

It now seems virtually certain that the West Croydon/Crystal Palace leg of the line will launch on the 23rd May with the New Cross to Dalston section opening from the 4th April.  On the 18th January, the construction team on the ELL handed the line over to TfL. Now it’s down to TfL to complete the work of training staff, testing trains and making sure signalling systems work. 

Last Updated on Thursday, 21 January 2010 09:32
Read more...
 
«StartPrev12345678910NextEnd»

Page 2 of 10