Forest Hill pools Open Day – 22 March and 5 April
Message from Helen Ferguson, Project Manager, Programme manager and Property at LBL:
Willmott Dixon Construction have been on site at Dartmouth Road for just over 2 months and in that time they have made a great start to the programme:
- The first few weeks were dedicated to enabling works, which included extending the hoarding line, carrying out remedial works to Louise House, setting up welfare facilities for the staff
- We received approval for all pre-commencement conditions from Lewisham Planning Department, which allowed Willmott Dixon to commence building works.
- Construction work began in early February with ground excavation and levelling; using crushed material from the demolition of the pool halls to form a ‘piling mat’, a temporary surface to carry the weight of heavy machinery such as the piling rig.
- To date Willmott Dixon have excavated and removed approximately 2,500m3 of soil, to be re-used on another site, and are currently carrying out piling works (piling 22 metres below ground level), in preparation for the new building’s foundations.